Thursday 29 December 2011

scaffold taken down at the rear.

Thursday 8 December 2011

Thursday 10 November 2011

Dormers cladded.


Dormers cladded in black cement board/wood effect.


- Posted using BlogPress from my iPad

Location:Sudbury

Monday 7 November 2011

Cladding dormer




- Posted using BlogPress from my iPad









Tyvek membrane and roof batten & black cement board cladding.

Location:Colchester,United Kingdom

Monday 10 October 2011

Finished tiling front



- Posted using BlogPress from my iPad



Front roof finished , velux chimney and lead flashing, tiles and fascia.

Tuesday 4 October 2011

Roof tiles

Roofers finishing off the front.



- Posted using BlogPress from my iPad

Thursday 22 September 2011

Chimney

Front view of the new fiberglass chimney




- Posted using BlogPress from my iPad

Location:Sudbury Suffolk

Wednesday 7 September 2011

stained glass and frame.

This is the stained glass for above the front doors. We had the frames handmade by Chilton joinery in Sudbury from a template, and they came back a perfect fit. The glass design was mine, both panels are a similar design with some slight differences. The stained glass panels were made by Andy Brooke, and a fantastic job he did too, they came back better than i'd hoped.

Saturday 20 August 2011

Frontage with soffit and fascia.





- Posted using BlogPress from my iPad

Saturday 13 August 2011

Front view with velux windows


This is the latest front view with 2 velux windows at the front, all trusses have been trimmed ready for bargeboard and soffit .


- Posted using BlogPress from my iPad



Wednesday 20 July 2011

Roofing felt and battens.



- Posted using BlogPress from my iPad

Saturday 16 July 2011

Roof day 3

Day 3 of roof building, dormers finished and kitchen trusses on,









- Posted using BlogPress from my iPad




View of kitchen extensions from 2nd floor.





View of top floor bedroom.











Inside kitchen.







Thursday 14 July 2011

View of the back of the houses and the roof dormers being built.





- Posted using BlogPress from my iPad

Wednesday 13 July 2011

Who says I don't update....

Here is the start of the roof, main roof is a hand cut roof.


- Posted using BlogPress from my iPad

Saturday 9 July 2011

Rear view










- Posted using BlogPress from my iPad

Location:Weeley Rd,,United Kingdom

Sunday 3 July 2011

Ready for the roof

iPad blogpress.

Steels in place and ready for roof to be delivered and fitted early July



Monday 6 June 2011


Massive steel supports that go from first floor to roof to form ridge beam.
A view of the steel from the road.

These are the massive steel posts that form the ridge beam and supports from first floor to roof.

Monday 31 January 2011

Latest photos of brickwork, front and rear complete.


- Posted using BlogPress from my iPad

Thursday 13 January 2011

updated front brickwork



Front almost finished with string course and name stone in place

Monday 10 January 2011

Latest update after all the snow throughout most of December, work commences in January.


should be brick built in a week or so.